Marlboro Street Rehabilitation Project

The City’s contractor, SUR Construction West, will begin work next week for the Marlboro Street Rehabilitation Project. The project will replace problematic water, drainage, and sewer mains along the corridor. Only sewer and drainage work is planned for the fall; work to replace water mains will occur in the spring of 2020.
 
Work this fall is expected to last approximately 2 months. Traffic will be reduced to one-way alternating along Marlboro Street for the majority of the project. This will be controlled by flaggers at either end of the work zone, and a third flagger for driveways as needed.
 
Work scheduled for next week includes mobilization of equipment and materials, installation of signage, and installation of sewer pipe and manholes. No utility service disruptions are planned at this time. 
 
If you have any questions regarding this post please call our office at 352-6550.